Timeline unknown
Tue, 08/22/2023 - 3:26pm
admin
By:
Amanda Mendez, Publisher
“It’s a big and important project, and we need to get it right the first time.”
The August 14 start date of repairs for the building known as the McClellan Building at Main and Center Streets has been postponed and has not yet been rescheduled.
The City of Willow Springs has been hearing official updates on the status of this building for thirteen months. In December, the board of aldermen declared it a dangerous building. In March, the building changed hands from one nonprofit to another. In July, new owner, the board of the Willow Springs Community Foundation approved an approximately $350,000 bid for work that would fix the building’s roof and stabilize the north wall. This work was scheduled to begin August 14.
During the board of aldermen meeting on August 17, WSCF Director Dean Aye’s update was that work has not begun because of a misunderstanding between the Foundation and their contractor, Base Construction, about the details in the scope of work.
“It became apparent [when we met early this month] that we weren’t in agreement on the scope of work,” Aye told the aldermen. “When we said ‘stabilize’ the north wall, they meant to the doorway. I meant to the roof.”
The structural engineer who designed the scope of work assured Aye that the plan as presented does stabilize the wall. Stabilizing the wall and repairing the roof have been the city’s main concerns with this building.
“But I want [them] to fix the whole thing, so we stopped and got more people involved in it,” Aye explained. “It’s a big and important project, and we need to get it right the first time.”
City Administrator Beverly Hicks reported to the board that she has also been in contact with Oke-Thomas, the project management firm.
“The way to move forward is to get everybody in the room again,” she suggested. “I’ve never met with Base, we’ve never had a preconstruction meeting, and that’s what needs to take place…We all have a part to play in this, and we certainly want it to be successful.”
“I don’t know what else we can do as long as we’re getting updates,” commented Alderwoman Kim Rich.
Aye promised “fresh numbers” as soon as the preconstruction meeting can take place. In response to a question from Howell County News, he said the WSCF does have the funds to complete the work that will stabilize the building.
The board of aldermen took no action regarding the building at this meeting.